REGIONAL TRANSPORTATION PROGRAM EXTENSION PROJECTS

The following projects are part of the Regional Transportation Program of the Measure C Extension. Approximately $357 million has been divided equally between the urban and rural areas of the County, and more than $12 million will pay for improvements to Fresno Yosemite International and Chandler Airports.

The funding for the Regional Transportation Program comes from three sources – fifty percent from Measure C, twenty percent from the State Transportation Improvement Program (STIP), and thirty percent from the Regional Transportation Mitigation Impact Fee program (RTMF). The RTMF program is developed and approved by the Fresno COG and Transportation Authority in conjunction with all local jurisdictions. It will become effective no later than January 1, 2010 and shall cover the entire 20-year period of Measure C Extension.

Fresno COG, the Authority’s Regional Planning Agency, will prioritize the Measure C Extension projects and will assign the funding allocations and schedule completion dates for each project. Projects will begin as funding from one or all the sources indicated above are made available as laid out in the Measure C Extension Regional Transportation Program Handbook (Short-Term).

Due to the complexity of prioritizing and ranking the Regional Transportation Program projects, the Regional Transportation Program has been divided into the Short-Term and the Long-Term Sub Programs. The Short-Term Sub Program will run from 2007 through 2017 and the Long Term Sub Program will reflect funding for 2017 to 2027. Review of the funding and schedules for projects to be programmed in the Long-Term Sub Program will not begin review until 2014. Updates to the projects in the Regional Transportation Program (and the Regional Transportation Handbook) will be made bi-annually to reflect any changes to project schedules or acceleration of the Program or projects.

Tier 1 Urban Projects

ID Project Name Project Description   Funding   Progress
A SR 180 East Seg II
[Map]
New multi-lane Freeway on State Route 180 East from Clovis to Temperance. This project is a holdover from the Original Measure C Expenditure Plan.   Measure C Extension:
$27.58 Million
STIP:
$60.13 Million
State Taxes:
$20 Million
  PROJECT COMPLETED (Construction began March 2008 and was completed in November 2010.) Total Project Costs $107.7M.
B SR 180 West Seg II (Brawley to Hughes/West)
[Map]
Three phase project. B1 - New Freeway on SR 180 West from Brawley to Hughes West. B2- Frontage Road (Realign Ronquio Blvd) B3-Landscaping & Irrigation.   Original Measure C:
$38 Million
Measure C Extension:
$5.31 Million
STIP:
$5.45 Million
SLPP:
$2.21 Million
RTMF:
$0.55 Million
  Phase B1 - Completed 12-08 / Phase B2 - In Progress / Phase B3 - Scheduled (See Detail Below)
  Phases:
 
B1 New Freeway on SR 180 West from Brawley to Hughes West. Total Phase Cost $38M   Original Measure C:
$38 Million
  PHASE COMPLETED 12/08 - - Grand Total Project Costs $83.1 Million
 
B2 Construct Frontage Road, Realign Ronquio Blvd and Install Traffic Signal. Total Phase Costs $7.519M   Measure C Extension:
$5.31 Million
SLPP:
$2.21 Million
  Design-COMPLETED / ROW-In Progress/ Construction-In Progress Anticipated End: 2014
 
B3 Install Landscaping & Irrigation on the new freeway from Brawley to Teilman Avenue (Hughes/West Connector). Total Phase Cost $5.122M   STIP:
$4.57 Million
RTMF:
$0.55 Million
  Design - In Progress (2012) Right of Way- In Progress (2013) Construction - Begin: 2015
C SR41/168/180
[Map]
New Braided Ramps adding capacity for safe connection between State Routes 41, 168 & 180. Funding accelerated with Measure C Extension and State Highway Operation & Protection Program - Mobility (SHOPP). One of the first Design/Build projects approved.   Original Measure C:
$12.7 Million
State Taxes:
$55 Million
  Due to cost savings the project has been accelerated and chosen as a Design/Build. Begin 2011 End 2013.
D Willow Avenue
[Map]
On Willow Ave from Barstow to Copper Ave complete to 6-Lane Divided Road and retrofit existing bike paths.   Measure C Extension:
$15.38 Million
Local Development Fees:
$3.75 Million
Federal Aid:
$4.34 Million
State Taxes:
$250,000
  Project to be built in 10 phases. Total costs of all phases is $23.713M
  Phases:
 
D1 Construct 2nd & 3rd northbound lanes with median, landscaping from Shepperd to Copper Ave. and traffic signal at Perrin Avenue.   Measure C Extension:
$6.35 Million
Local Development Fees:
$1.59 Million
  Design and Right of Way Begin: 2014 End: 2015 / Construction Begin: 2015 End: 2016
 
D2 Construct outside travel lane on the East side of roadway, median and landscaping from Teague to Perrin Ave.   Measure C Extension:
$322 Million
Local Development Fees:
$453,000
  PHASE D2 COMPLETED IN 2009. TOTAL COST $775,000
 
D2A Install traffic signal and intersection improvements at Willow and Shepherd Avenue.   Measure C Extension:
$353 Million
Local Development Fees:
$312,000
Federal Aid:
$1.78 Million
  PHASE D2A COMPLETED TOTAL COST $2.446M Began: 2007 Ended: 2008
 
D3 Construct outside travel lane on the East side of the roadway, sidewalk, street lights and landscaping from Alluvial for 1/4 mile.   Measure C Extension:
$554 Million
Local Development Fees:
$139,000
  Begin: 2011/2012 End: 2013/2014
 
D4A Construct South bound lane on West side of Roadway, median, curbs and landscaping from Teague to Shepherd Ave.   Measure C Extension:
$289 Million
Local Development Fees:
$72,000
  PHASE D4A COMPLETED IN 2009. TOTAL COST $361,000
 
D4B Widen to 3 Southbound lanes from Shepherd Avenue to Behymer Avenue.   Measure C Extension:
$2.86 Million
Local Development Fees:
$715,000
  UNDER CONSTRUCTION Begin: 2009 End: 2013
 
D5 Widen to 3 Southbound lanes from Decatur Avenue to Shepherd Avenue.   Measure C Extension:
$1.34 Million
Federal Aid:
$2.56 Million
  Design-COMPLETED / ROW-IN PROGRESS / Construction - Beg: 2012 End: 2013
 
D6 Widen to 3 Southbound lanes form International Avenue to Copper Avenue.   Measure C Extension:
$571 Million
Local Development Fees:
$143,000
  Design-2017 / Construction - Begin: 2017 End: 2018
 
D7 Widen to 3 Southbound lanes from Herndon Avenue to Alluvial Avenue.   Measure C Extension:
$1.29 Million
Local Development Fees:
$322,000
  Design - Begin: 2014 End: 2015 / Right-of-Way - Begin: 2014 End: 2015 / Construction - Begin: 2017 End: 2018
 
D8 Retrofit Willow Avenue to six lanes from Barstow Ave. to Herndon Ave., provide intersection improvements at Bullard Avenue and will also install bicycle paths. Project phase includes design, right of way purchase and construction.   Measure C Extension:
$1.45 Million
State Taxes:
$250,000
  Design-IN PROGRESS / ROW-IN PROGRESS / Construction - Begin: 2012 End: 2013
E Temperance Avenue
[Map]
Widen Temperance Ave from Bullard to Shepherd Ave to a 4-Lane Divided Road.   Measure C Extension:
$3.14 Million
Federal Aid:
$455,000
SLPP:
$2.03 Million
  This project will be built in 3 segment phases. Total Project Costs $5.624M
  Phases:
 
E1 Widen to 4-Lane divided expressway from the Enterprise Canal to Nees Avenue and install a traffic signal at Nees Avenue. This phase includes design, right-of-way and construction.   Measure C Extension:
$1.44 Million
SLPP:
$728,000
  Design - IN PROGRESS/ Right of Way- IN PROGRESS / Construction- IN PROGRESS Anticipated End: 2014
 
E2 Widen to a 4-Lane divided Expressway from Bullard Avenue to Herndon Avenue and install traffic signal at Sierra Avenue. This phase includes design and construction.   Measure C Extension:
$1.49 Million
Federal Aid:
$101,000
SLPP:
$1.3 Million
  Design-COMPLETED / Construction-IN PROGRESS Anticipated Completion Date: 2013
 
E3 Widen to a 4-Lane Expressway with sidewalk, street lights and landscaping from Nees to Shepherd Avenue with traffic signal at Shepherd Avenue. This phase includes design, right-of-way and construction.   Measure C Extension:
$215,000
Local Development Fees:
$354,000
  Design - Begin: 2012 End: 2013 / Construction - Begin: 2013 End: 2015
F Ventura Boulevard
[Map]
Widen Ventura Boulevard from State Route 41 to State Route 99 to a 4-Lane Divided Road. This project includes design, right-of-way and construction.   Measure C Extension:
$6.14 Million
Local Development Fees:
$200 Million
  Design-COMPLETED / ROW Begin: 2011 End: 2012 / Construction Begin: 2013 End 2014
G SR99 Monterey Bridge Demolition
[Map]
Demolish the Monterey Street Bridge in downtown Fresno from Broadway to Golden State Boulevard for safety reasons. Original scope was to retrofit bridge however after inspections it was deemed unsafe to repair and too costly to replace.   Measure C Extension:
$1.6 Million
  Construction-Demolition IN PROGRESS
H California Ave Widening
[Map]
Widen California Ave to a 4-Lane Divided Road from Ventura Ave to Fruit Ave. This project has been phased into two segments. The first segment is completed. The second segment will be funded in the Long-Term Regional Transportation Program (2017-2027).   Measure C Extension:
$2.2 Million
Funding Source TBD:
$12.6 Million
  This project has been split into two segment phases. Phase 1 COMPLETED Phase 2 The funding and schedule of the 2nd Phase will be set in the Long-Term Program which will be under review by Fresno COG in 2014.
  Phases:
 
H1 Widen California Avenue from West to Fruit Avenues to a 4-Lane Divided Arterial   Measure C Extension:
$2.2 Million
  PHASE H1- COMPLETED. TOTAL COST FOR THIS PHASE WAS $2.2M
 
H2 Widen California Avenue to a 4-Lane Divided Arterial Road from Fruit Avenue to Ventura Avenue.   Funding Source TBD:
$12 Million
Measure C Extension:
$692 Million
  Design work in the amount of $692,000 will be done in 2018. ROW and Construction of Phase H2 will be programmed in the Long-Term sub program. Review of the Long-Term program will begin at Fresno COG in 2017 with estimated costs of $12 million.
I Peach Ave Widening
[Map]
Widen Peach Ave to a 4-Lane Divided Road from State Route 180 to Jensen Ave. Total project costs $25.08M. This project is split into four phases. Phase I2A, I2B, I2C and I3. The ultimate project will widen Peach Ave from two to four lanes with median l   Measure C Extension:
$8.99 Million
Local Development Fees:
$2.91 Million
SLPP:
$3.65 Million
State Taxes:
$867,000
  Phase I2A Begin 2011 End 2013 / Phase I2B Begin 2010 End 2018 / Phase I2C Begin 2017 End TBD / Phase I3 Begin 2009 End 2014
  Phases:
 
I3 I3 will Widen Peach Avenue to 4 Lanes from State Route 180 to Butler Avenue. It will also provide median landscaping, protected left-turn lanes, bike lanes, landscaping, streetlights and installation of new traffic signals at Huntington Boulevard. Total P   Measure C Extension:
$8.06 Million
SLPP:
$3.65 Million
State Taxes:
$600,000
  Design: Begin 2009 / ROW: Begin 2010 / Construction: Begin 2013
 
I2B Phase I2B will widen Peach Avenue from Butler Avenue to Church Avenue (SJV Railroad Crossing) from two lanes to four lanes with protected left-turn lanes, median landscaping, bike lanes and streetlights.   Measure C Extension:
$682,000
Local Development Fees:
$1.9 Million
  Design: Begin 2010 / ROW: Begin 2016 Construction: Begin2017
 
I2C Phase I2C will purchase Right-of-Way to widen Peach Avenue to 4 lanes between Jensen Avenue to Butler Avenue providing median landscaping, protected left-turn lanes, bike lanes, streetlights and traffic signal at Butler Avenue. This phase is for Right-of-   Local Development Fees:
$1.01 Million
Funding Source TBD:
$15.69 Million
  Design: Begin 2017/18 / ROW: Begin 2017/18 / Construction: TBD
 
I2A Install a new traffic signal on Peach Avenue at Church Avenue   Measure C Extension:
$250,000
State Taxes:
$267,000
  Begin 2011 End 2013
J SR41 Auxiliary Lane
[Map]
Widen State Route 41 and build Auxiliary Lanes and improve on/off ramps from Tulare Street to O Street. This project will be programmed in the Long-Term Regional Transportation Program.   Funding Source TBD:
$21.59 Million
  The funding and schedule for this project will be set in the Long-Term Program which will begin review at Fresno COG in 2014.
K Herndon Ave Widening
[Map]
Complete the widening of Herndon Ave to a 6-Lane Divided Road from State Route 99 to De Wolf Ave and retrofit existing bike paths. This project has been divided into 12 segment phases with a total cost of $115.844M. $94.511M has yet to be programmed.   Measure C Extension:
$9.6 Million
Federal Aid:
$8.66 Million
State Taxes:
$295,000
Local Development Fees:
$2.82 Million
Funding Source TBD:
$94.51 Million
  This project was split into 12 segment phases. (As of 2010 Phase 4 has been dropped.) Phases K8 and K9 and the construction portion of Phases K10 will be programmed in the Long-Term Sub Program (2017-2010).
  Phases:
 
K5B Widen East-Bound Herndon Avenue to 6-Lanes from Blythe Avenue to Brawley Avenue. Total Project Costs $1.936 million.   Measure C Extension:
$1.12 Million
SLPP:
$818,000
  Design/ROW/Construction Beg 2012 End 2014
 
K5C Widen West-bound Herndon Avenue to 6-Lanes from Blythe Avenue to Brawley Avenue. Total Project costs $928,000.   Measure C Extension:
$108,000
Federal Aid:
$820,000
  Design: 2013-2014 / ROW: 2014-2015 / Construction: 2015-2016
 
K07 Widen Herndon Ave to 6-Lanes from SR99 to Weber Avenue and install dual left-turn lanes at Golden State Boulevard. THIS PHASE IS COMPLETED. Total Project Costs $5.524 Million   Measure C Extension:
$996,000
Federal Aid:
$4.53 Million
  Design - COMPLETED ROW - COMPLETED Construction - COMPLETED
 
K03 This phase will widen Herndon Avenue from Temperance Ave to DeWolf Ave, provide dual left-turn lanes, install traffic signals and sidwalks. Total Project Costs $12.403 million.   Measure C Extension:
$9.92 Million
Local Development Fees:
$2.48 Million
  Design: Beg 2015 End 2017 / ROW: Beg 2016 End 2017 / Construction: Beg 2017 End 2019
 
K06 This phase widened Herndon Avenue from Valentine Avenue to Marks Avenue to 6-Lanes providing median landscaping. Total Project Costs $2.936 million.   Measure C Extension:
$807 Million
Federal Aid:
$2.13 Million
  THIS PHASE IS COMPLETED.
 
K09 Construct a 6-Lane Underpass under the Union Pacific Rail Road Crossing located at Herndon and Weber Avenues.   Funding Source TBD:
$61.37 Million
  This phase will be programmed in the Long-Term Program (2017-2027).
 
K10 Widen Herndon Ave to 6-Lanes from Weber Ave to Polk Ave. The Design portion of this phase in programmed in the Regional Transportation Short Term Program. The Construction portion of this phase will be programmed in the Long-Term Program (2017-2027).   Measure C Extension:
$5.42 Million
Local Development Fees:
$1.36 Million
  Design: Begin 2017 End 2018 / The funding and schedule for Construction will be set in the Long-Term Program which will begin review at COG in 2015.
 
K02 Widen Herndon Ave to 6-Lanes from Clovis Avenue to Fowler Avenue providing dual left turn lanes, install traffic signals, sidewalks and medians curb and gutters. Total Project Costs $2.063 million.   Measure C Extension:
$1.23 Million
SLPP:
$799,000
Local Development Fees:
$38,000
  Design: Beg 2009 End 2011 / ROW: Beg 2009 End 2012 / Construction: Beg 2013 End 2015
 
K01 This phase widened Herndon Ave to 6-lanes from Willow Ave to Clovis Ave. This phase also installed traffic signals, sidewalks, landscaping medians, street lights and curb and gutter work.   Measure C Extension:
$646,000
State Taxes:
$295,000
Federal Aid:
$1.96 Million
Local Development Fees:
$915,000
Original Measure C:
$120,000
  COMPLETED
 
K5A Widen Herndon Avenue to 6-Lanes from Brawley Avenue to Valentine Avenue. Total Project Costs $2.951 million.   Measure C Extension:
$1.17 Million
Federal Aid:
$1.77 Million
Local Development Fees:
$15,000
  Design: Beg 2010 End 2012/ ROW: Beg 2011 End 2012 / Construction: Beg 2012 End 2014
 
K08 This phase will be programmed in the Long-Term Regional Transportation Program (2017-2027). Funding costs is estimated at $26.365. This project will widen the Herndon Avenue Undercrossing at SR99 to five lanes.   Funding Source TBD:
$26.36 Million
  TBD
 
K11 Widen BNSF Rail Road Overpass to 6-Lanes. The Design only portion of this phase ($858,000) is programmed in the Short-Term Regional Transportation Program and the Right-of-Way and Construction will be programmed in the Long-Term Program.   Measure C Extension:
$6.39 Million
Local Development Fees:
$1.5 Million
  Design - Begin 2012 End 2016 ROW & Construction TBD
L Shaw Ave Upgrades
[Map]
Improve Shaw Ave from Sunnyside to McCall to 6-Lane Divided Road upgrading traffic signals and grade crossings.   Measure C Extension:
$9.82 Million
Local Development Fees:
$2.45 Million
  This project has been split into 2 segment phases in the Short-Term Sub Program.
  Phases:
 
L1 Widen to a 6-Lane divided Expressway, street lights sidewalk and traffic signal from Local to DeWolf Avenue.   Measure C Extension:
$1.55 Million
Local Development Fees:
$387,000
  Design - Begin: 2011 End: 2013 / ROW - Begin: 2011 End: 2013 / Construction - Begin: 2013 End: 2014 /
 
L2 Widen to a 6-Lane divided Expressway, install outside travel lane, street lights, median, landscaping and undercrossing from DeWolf to McCall Avenue.   Measure C Extension:
$8.27 Million
Local Development Fees:
$2.07 Million
  Design - Begin: 2012 End: 2014 / ROW - Begin: 2014 End: 2015 / Construction - Begin: 2014 End: 2016
M SR 99 Interchanges
[Map]
Improve State Route 99 Interchanges at North and Cedar Avenues. This project will be funded in the Long-Term Regional Transportation Program (2017-2027).   Funding Source TBD:
$81.61 Million
  The funding and schedule for this project will be programmed in the Long-Term Sub Program which will be under review at COG in 2014. Project Schedule TBD
N Veteran’s Boulevard
[Map]
This project has been split into two segment phases. Phase 1 covers Design/ROW of a Freeway Interchange & Grade Separation at UPRR crossing & Golden State Blvd. Phase 2 will connect the Interchange to Shaw & Herndon and will be funded in the Long Term Pr   Original Measure C:
$8.84 Million
Measure C Extension:
$3.25 Million
STIP:
$14.87 Million
RTMF:
$4.26 Million
Local Development Fees:
$500,000
  Phase 1. Design - Begin: 2008 End: 2011 Phase 1. ROW - Begin: 2016 End: 2017 Phase 2. Design - Begin: 2010 End: 2012 Phase 2. ROW - Begin: 2016 End: 2017 Construction for both phases to be programmed in the Long-Term Program (2017-2027).
  Phases:
 
N1 Design of Veterans Boulevard to its ultimate six-lanes between Barstow Ave and Bullard Ave, with a new Over Crossing of SR 99 a bridge spanning Golden State Blvd, at grade separation of rail road crossing; 4-lanes from Bullard to Herndon & Barstow to Shaw   Original Measure C:
$12.09 Million
STIP:
$14.87 Million
RTMF:
$4.26 Million
  Phase N1 is Design and ROW only. Design: Beg: 2008 End: 2011 ROW - Beg: 2016 End: 2017 Construction to begin in Long-Term Program (2017-2027).
 
N2 Phase N2 will Connect SR99 Interchange to Shaw & Herndon Avenues with 4-lanes from Bullard to Herndon and Barstow to Shaw. The project will include traffic signals at SR99 at Shaw, Bullard & Herndon Avenues & the Golden State Blvd connector roadway. Desi   Original Measure C:
$765,000
Local Development Fees:
$2.61 Million
  Phase N2. Design - Beg: 2010 End: 2012 Phase N2. ROW - Beg: 2016 End: 2017 Construction to be programmed in the Long-Term Program (2017-2027).


Tier 1 Rural Projects

ID Project Name Project Description   Funding   Progress
A SR 180 West
[Map]
Create passing lanes in each direction on State Route 180 West (Whitesbridge Road) from Yuba Ave to James Ave.   Measure C Extension:
$12.28 Million
  Design- IN PROGRESS Right of Way- Begin: 2012 End: 2013 Construction-Begin: 2013 End: 2014
B SR 180 East Seg III
[Map]
Widen State Route 180 East from Temperance to Academy Ave to a 4-Lane Divided Expressway. PROJECT COMPLETED-TOTAL PROJECT COSTS $78.443M   Original Measure C:
$30.56 Million
Federal Aid:
$19.61 Million
STIP:
$28.27 Million
  PROJECT COMPLETED. Original Measure C Program Funds. This project was accelerated using Original Measure C funds and leveraging Federal Stimulus ARRP funds. Began: 2009 Completed: 2011
C SR 180 East Seg IV
[Map]
Widen State Route 180 East from Academy to Trimmer Springs to a 2-Lane Expressway on 4-Lane right-of-way. This project has been accelerated using Original Measure, State and Local Partnership and Extension Measure Regional Transportation Mitigation Fee (   Original Measure C:
$13.13 Million
Measure C Extension:
$9.44 Million
SLPP:
$11.55 Million
RTMF:
$3.47 Million
  Part of the Original Measure C Program. Design- In Progress; Right of Way- In Progress; Construction phase accelerated to begin in 2013.
D SR 180 East Seg V
[Map]
Widen SR180 East to a 2-Lane Expressway from Trimmer Springs to Frankwood Avenue. The Design and part of the Right of Way portion of this project was accelerated using $13.589 Original Measure funds. The total project costs is $90.948M.   Original Measure C:
$13.59 Million
Measure C Extension:
$19.6 Million
STIP:
$57.76 Million
  Part of the Original Measure C Program. Design Phase- In Progress / Right of Way Phase - In Progress / Construction Phase - Begin: 2016 End: 2017
E Friant Road Widening
[Map]
Widen Friant Road from Copper Ave to Millerton to a 4-Lane. Total Project Costs $4.120 Million.   Measure C Extension:
$4.12 Million
  PROJECT COMPLETED Began: 2008 Ended: 2009
F Golden State Boulevard
[Map]
Corridor and Economic improvements to Golden State Boulevard from American Ave. to Tulare County line. Costs for Right-of-Way and Construction to be determined after the design portion is completed. Total Project Cost to be determined after Design phase   Measure C Extension:
$6.83 Million
  Design-In Progress/ Environmental- Begin: 2013 End: 2014 / Right of Way and Construction to be programmed in the Long-Term Program which will be under review at COG beginning 2016. Total Project Cost to be determined after Design.
G SR 269 Bridge Improvement
[Map]
Construct a new bridge and channel on SR269 between SR198 and Huron to address seasonal road closures due to flooding. This project will be programmed in the Long-Term Regional Transportation Program (2017-2027).   Funding Source TBD:
$39.8 Million
  This project's funding and schedule will be programmed in the Long-Term Program which will begin the review process at COG in 2014.
H SR 180 West I5 Extension
[Map]
Route Adoption Study to extend State Route 180 West to Interstate 5 as a 3-Lane undivided highway. This $82.761 million project will be scheduled in the Long-Term Regional Transportation Program which will begin review in 2014.   Funding Source TBD:
$82.76 Million
  The funding and schedule for this project will be programmed in the Long-Term Program which will begin the review process by COG in 2014.
I Mountain View Ave Widening
[Map]
Widen Mountain View Ave to a 4-Lane Divided road from Bethel Ave to the Tulare County line.   Measure C Extension:
$15.22 Million
SLPP:
$8.84 Million
  Project under Design and ROW phase. Construction - Begin: 2012 End: 2013
J Academy Ave Widening
[Map]
Widen Academy Ave from Manning Ave to Industrial Way in Parlier. PROJECT COMPLETED 08/12 WITH $1.6 IN COSTS SAVINGS.   Measure C Extension:
$1.95 Million
  Design/Right of Way- COMPLETED / Construction-COMPLETED
K SR99 American Ave Interchange Improvement
[Map]
Improve American Avenue Interchange on State Route 99. This project will be programmed in the Long-Term Regional Transportation Program (2017-2027).   Funding Source TBD:
$10.38 Million
  The funding and schedule of this project will be programmed in the Long-Term Program which will begin the review process at COG in 2014.
L I-5 Interchange Improvement
[Map]
Construct Interchange Improvement at the State Route 99 Interstate 5 Connection. This project will be programmed in the Long-Term Regional Transportation Program (2017-2027).   Funding Source TBD:
$18.24 Million
  The funding and schedule for this project will be set in the Long-Term Program which will begin the review process at COG in 2014.


Tier 2 projects, both Urban and Rural, are listed below and are in a generalized priority order. Projects will move forward as they become deliverable not in the order they are listed below. The Measure C Extension Expenditure Plan is reviewed every two years by Fresno COG to determine project readiness. The project funding order will be determined by Fresno COG during their biannual review and become deliverable based on the project cost benefit, project readiness, and funding availability.

Tier 2 Urban Projects

ID Project Name Project Description   Funding   Progress
AA SR99 Ramp Improvement Improve on and Off Ramps on State Route 99 at Stanislaus and Tuolumne to improve downtown Fresno access.     No funding available at this time. COG and the Authority will review funding availability every two years.
BB SR 41 O Street Ramps Widen and build Auxiliary Lanes and Improve On/Off Ramps on State Route 41 and O Street Ramps.     No funding available at this time. COG and the Authority will review funding availability every two years.
CC Friant Road Widening Widen Friant Road to a 6-Lane Divided Road from Shepherd Ave to Copper Ave.     No funding available at this time. COG and the Authority will review funding availability every two years.
DD SR 99 Shaw Ave Interchange Improve Interchange on State Route 99 at Shaw Ave.     No funding available at this time. COG and the Authority will review funding availability every two years.
EE Traffic Synchronization Coordinate Traffic Signals in selected regionally significant corridors in the cities of Fresno and Clovis.     No funding available at this time. COG and the Authority will review funding availability every two years.
FF Herndon Ave Widening Continue the Widening of Herndon Ave to a 4-Lane Divided highway from DeWolf Ave to McCall Ave.     No funding available at this time. COG and the Authority will review funding availability every two years.
GG SR99 Auxiliary Lanes Add North and Southbound Auxiliary Lanes to State Route 99 from Fresno Ave to Clinton Ave.     No funding available at this time. COG and the Authority will review funding availability every two years.
HH Blackstone Ave Turn Lanes Add dual left turn lanes to the Intersection of Blackstone and Shields Ave.     No funding available at this time. COG and the Authority will review funding availability every two years.
II SR 99 Shields Ave Overcrossing Construct a new Overcrossing at Shields Ave on State Route 99.     No funding available at this time. COG and the Authority will review funding availability every two years.
JJ McCall Widening Widen McCall Ave to a 6-Lane Divided Road from Griffith Ave to Shaw Ave.     Projects under prioritization review with Fresno COG at this time.
KK Shepherd Ave Widening Widen Shepherd Ave to a 4-Lane Divided Road from Cedar Ave to State Route 168.     Projects under prioritization review with Fresno COG at this time.
LL SR 41 Auxiliary Lanes Add North and Southbound Auxiliary lanes to State Route 41 from McKinley Ave to Shields Ave.     No funding available at this time. COG and the Authority will review funding availability every two years.
MM SR99 Widening Widen State route 99 to a 6-Lane Freeway from Ashlan Ave to the Madera County Line.     No funding available at this time. COG and the Authority will review funding availability every two years.
NN Traffic Management Center Make upgrades to Caltran’s Traffic Management Center.     No funding available at this time. COG and the Authority will review funding availability every two years.
OO Minnewawa 4-Lane Project Complete the widening of Minewawa Ave to 4-Lanes from Shepherd Ave to Copper Ave.     No funding available at this time. COG and the Authority will review funding availability every two years.


Tier 2 Rural Projects

ID Project Name Project Description   Funding   Progress
AA SR99 Interchange Improvement Improve the Central and Chestnut Interchanges on State Route 99.     No funding available at this time. COG and the Authority will review funding availability every two years.
BB SR 145 Widening Widen State Route 145 to a 4-Lane Divided Highway from Nielson Ave to South of the City of Kerman.     No funding available at this time. COG and the Authority will review funding availability every two years.
CC SR 33 Widening Widen State Route 33 to a 4-Lane Divided Highway at the State Route 180 Intersection.     No funding available at this time. COG and the Authority will review funding availability every two years.
DD Academy Parkway Construct a New Diagonal Connector Road south of Mountain View to State Route 99 Kamm/Bethel Interchange.     No funding available at this time. COG and the Authority will review funding availability every two years.
EE SR 41 Interchange Upgrade Upgrade the Intersection and Interchanges on State Route 41 at Central and American Avenues.     No funding available at this time. COG and the Authority will review funding availability every two years.
FF Millerton Road Widening Widen Millerton Road to a 4-Lane Divided Road from Friant to Sky Harbor.     No funding available at this time. COG and the Authority will review funding availability every two years.
GG Manning Ave Widening Widen Manning Ave to a 4-Lane Divided Road from the Reedley City limits to Alta.     No funding available at this time. COG and the Authority will review funding availability every two years.
HH SR 43 Widening Widen State Route 43to a 4-Lane Undivided Highway from the City of Selma to the Kings County Line.     No funding available at this time. COG and the Authority will review funding availability every two years.
II McCall Ave Connection Complete the 4-Lane Connection on McCall Ave from Shaw Ave to State Route 168.     No funding available at this time. COG and the Authority will review funding availability every two years.
JJ SR 180 E Seg VI Convert State Route 180 East to a 2-Lane Expressway on new alignment from Frankwood Ave to Cove.     No funding available at this time. COG and the Authority will review funding availability every two years.